on 07-02-2009 10:51 AM
Hello Gurus,
Does someone know if there exists a standard report allowing us to display in mass the system and the user status assigned to a WBS?
Or do we have to write a specific one using function BAPI_BUS2001_GET_STATUS?
Kind regards
Chris
u can use structure reports to see the status...
CN41 - project
CN42N - Project Definition of several projects
CN43N - WBSE of several projects
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
go to cn41n and execute by entering the list of wbs or project
and select the status from the layout.
ashis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |