I am creating project from Sales Order Ex creating sales 1-07-09 and delivery date 1-12-09 here client rquirement is automaticaly project activities has to plan according to sales order delivery date.

how i can achieve this please give me your valuable inputs

Regards

etr

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

closed

Former Member
0 Kudos

means i have to maintain duration in standard WBS and Satandard Network level

former_member203108
Active Contributor
0 Kudos

This message was moderated.

former_member203108
Active Contributor
0 Kudos

This message was moderated.

Former Member
0 Kudos

Hi,

Please refer step by step what you have to do for assembly processing.

https://wiki.sdn.sap.com/wiki/display/PLM/Assembly%20Processing%20with%20SAP%20PS

Rgds

Sudhir reddy

Former Member
0 Kudos

i created a sales order today 02-07-09 and given delivery date 31-07-09. in cj20n project start date 02-07-09 and finish date 31-07-09 ok this is fine .

but in WBS level one and two Basic Start&Fin Dat and Early Sart&Fin Forecast Sart&Fin dates all are 31-07-09 only

even in Networks and activity all Start and Fin dates also 31-07-09 only

please give me your valuable in puts

former_member203108
Active Contributor
0 Kudos

This message was moderated.

Former Member
0 Kudos

please tell me what are the configuration steps needed for that

Former Member
0 Kudos

Hi,

I don't think extra configurtions you need to do other than as normal in PS.

refer to link:

https://wiki.sdn.sap.com/wiki/display/PLM/Assembly%20Processing%20with%20SAP%20PS

Rgds

Sudhir Reddy

Former Member
0 Kudos

While defining material master detail make sure the strategy defined is for assembly processing ( like 83 or 85).

Regards

Avisek Bhardwaj

Former Member
0 Kudos

Hi

In material master maintain Planning Strategy 85

You have use order type PS04 for assembly processing

In OPSC maintain the order type related settings and the number range ( CO82) for the order type.

Create one network profile and assign the order type in to that. (OPUU)

Thanks

S.Murali

former_member203108
Active Contributor
0 Kudos

use assembly processing...system will schedule the network backwards using the delivery date from sales order...