error during project release?

former_member221039
Active Participant
0 Kudos

Dear PS experts,

I have created project quotation using dp82,

while release the project the following error is coming and project is releasing

pl help in giving solution how to release

=================================================

Enter a distribution rule for Sales document item without a validity limit

Message no. KD059

Diagnosis

The settlement profile used requires you to define a distribution rule for Sales document item. For period 004 2009, however, you have not created a distribution rule for Sales document item.

Procedure

Create a distribution rule for Sales document item without a validity limit, because, if the distribution rule does have a validity limit, the system always issues this message in the period following the last valid period.

You can also use a different settlement profile that does not require such a distribution rule, or change the settlement rule used.

===============================================

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

Go to OK07 select your settlement profile and change the

In the Valid receviers screen

Sales order 1 Settlment Optional

Thanks

S.Murali

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Goto Settlement profile that you have used for your sale order and allow valid receivers as 'SETTLEMENT OPTIONAL' you should not make it 'SETTLEMENT REQUIRED'.

If incase no receiver is allowed in the profile you are using then allow respective receivers as mentioned in the default object type field atleast in the valid receivers screen as mentioned above.

Rgds

Sudhir Reddy