CJI3- Report Further Selections-Partner Cost center

Former Member
0 Kudos

HI all,

I have requirement from the client.

While retreving the data from the standard report CJI3.

If he gives the WBS Element in the selection criteria and execute you get a list of actual line items posted .

If this WBS Element is being settled against a Cost centre.Settlement entries also is viewed in this list and in the field Partner Cost center, the cost center is seen.

There is a requirement from the client to give in the selection criteria both the WBS Element and Settlement Cost centre to give the list of items posted.

Can you please give me any pointers to get the report in this manner of WBS Element and it cost centre's settled.

if not this report any other report..

Thanks in advance for the help..

Regards,

Suresh

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member203098
Active Contributor
0 Kudos

Hi,

As hemanth told there is no standard report for your requirement.

Try this (S_ALR_87013619 - Range: Assigned Orders/WBS Elements) it may help you.

Regards,

Nag.

Former Member
0 Kudos

Hi

I do not think there is any standard report. You need to develop it. It will be based on the tables-PROJ, PRPS,COBRB and COEP.

Regards