on 04-27-2006 3:57 AM
SRM upgrade to 5.0, CCM 2.0, R/3 4.6C
Hi everyone,
I am hoping to see if someone can share some insight on this issue:
The current system (SRM 2.0) was creating separate reservations for each line item in one single shopping cart (multi line items). I believe that now
SRM has a more robust functionality that it will allow multiple line items to be grouped to single reservations depending on the vendor/acct asignment/ship tos/ etc like it does w/ POs. I believe this is a standard functionality. I was also told that if this is not there will be a BADI for this. If this a yes, would someone briefly give me how the system groups the items into single reservation in R/3?
Thank you for reading this message.
Jay Park
Hi everybody!!
Does anybody now if the action of requesting a SC can built up a commitment. If the approver reject the SC the commitment should be rejected. In the PO creation the commitment shouldn't be created.
Is that possible? if it is, can anybody give me some idea how it could be done.
thanks for your attention
Best regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
I think you can use the badi BBP_BS_GROUP_BE, method GROUP_RS_BACKEND for this. In export table, each line with the same refnumber will be grouped in one reservation. One refnumber correspond to one reservation.
Rgds,
Pierre
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.