HI Expert,
here we need a scenario, like...user can only do cost element based planning against WBS.
He should not be allowed to enter any manula cost directly against WBS.
How to address this issue.
thanx in adv.
regards
Ashis
Hi,
Try CJR2. Here you can do cost element planning against WBSE.
Regards,
Nag
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Go to CJR2 t-code select the layout 1-702 and enter the wbs, cost element, periods, year and version and execute the transaction. Then enter the values and save.
Remove the autorization for CJ40.
Rgds
Sudhir Reddy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Give Authorization for CJR2 and remove CJ40 from authorization.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.