restriction to only cost element based planning against WBS

Former Member
0 Kudos

HI Expert,

here we need a scenario, like...user can only do cost element based planning against WBS.

He should not be allowed to enter any manula cost directly against WBS.

How to address this issue.

thanx in adv.

regards

Ashis

Accepted Solutions (1)

Accepted Solutions (1)

former_member203098
Active Contributor
0 Kudos

Hi,

Try CJR2. Here you can do cost element planning against WBSE.

Regards,

Nag

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Go to CJR2 t-code select the layout 1-702 and enter the wbs, cost element, periods, year and version and execute the transaction. Then enter the values and save.

Remove the autorization for CJ40.

Rgds

Sudhir Reddy

Former Member
0 Kudos

Hi,

Give Authorization for CJR2 and remove CJ40 from authorization.

Regards,