Histogram "Capacity Overview"

Former Member
0 Kudos

Dear all,

when i display the Capacity Overview in the Project Planning Board, and display Work Center "with available capacity 40 Hr/Day" as Histogram, the Capacity Load Utilization in the Histogram in the table area of the Capacity Overvie displays the available capacity as 200 Hr which means 200 Hr/Week

why it calculate it and displays it per week ????????????

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

If your capacity planning table set for capacity week (CW) then it will calculate for a week.

Otherwise check your workcenter no of capacity in capacity tab, if the no .of capacity is 5 then it will show 200 hrs.

Only these two above possibilities will make the available capacity to 200 Hrs.

Please check and revert back

Thanks

S.Murali

Former Member
0 Kudos

This message was moderated.

Former Member
0 Kudos

hi SMD,

can you guide me about change "Capacity week" on capacity planning board.

I want the system calculate follow days not week.

Thanks for your help.