on 06-30-2009 5:39 PM
Dear all,
when i display the Capacity Overview in the Project Planning Board, and display Work Center "with available capacity 40 Hr/Day" as Histogram, the Capacity Load Utilization in the Histogram in the table area of the Capacity Overvie displays the available capacity as 200 Hr which means 200 Hr/Week
why it calculate it and displays it per week ????????????
Hi
If your capacity planning table set for capacity week (CW) then it will calculate for a week.
Otherwise check your workcenter no of capacity in capacity tab, if the no .of capacity is 5 then it will show 200 hrs.
Only these two above possibilities will make the available capacity to 200 Hrs.
Please check and revert back
Thanks
S.Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.