Dear all,

In Project Builder (CJ20N), I'm using the mass change to change the usage of a milestones, but the functions are not created. Is it a system behavior or a program error?

Accepted Solutions (0)

Answers (2)

Answers (2)

0 Kudos

A LSMW solved the problem.

Former Member
0 Kudos

Hi

but the functions are not created

Please clarify on this what u mean by functions

If you are meaning the functions = Usage, if yes

Then you need to create the milestone usage in SPRO

Project System --> Templates --> Standard milestone --> Define Standard milestone usage

Once you create the usage in SPRO then it will available for mass change.

Thanks

S.Murali

Edited by: S. Murali on Jul 1, 2009 10:04 AM

0 Kudos

Hi Murali.

I created the milestone usage in SPRO. After, in t-code CN12, I created standard milestone with a function to release following activities. This is the function that is not created in milestone when I use the mass change.

Thanks

Former Member
0 Kudos

Hi

Whether your issue is solved?, if Yes please close the thread. If not solved kindly give us the exact problem which you getting.

Thanks