Hi

The customer has sent free text POs to their vendors with one quantity and one unit of meassure but the invoice contains another quantity and UoM. The price is correct and the received quantity is right only that it's written in another UoM in the invoice.

Since the invoice is interpreted through a third party application the customer needs to change the UoM in the PO in SRM. When trying to do so we get a message telling us it is not possible and the old UoM stays.

The G/R has been deleted before trying to change the UoM.

Shouldn't it be possible to change the UoM of an ordered PO?

Extended Classic scenario, SRM 5.0.

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member206968
Active Contributor
0 Kudos

Hi,

Its not possible for changing UOM of a PO created from shopping cart. This is because system compares shopping cart qty with Po qty and it will not be possible to do if uom is different.

For you, alternate option is to delet existing conf. Create a new line item in PO with matching details and delete the original item. Order the Po and create new receipt.

Regards,