on 06-30-2009 9:47 AM
The issue is as follows:
We want to trigger an alert when a purchase requisition remains open for 5 days.
How can we achieve this using solman?
Process:
1. Create Purchase Requisition (PR)
2. Release PR
3. Create Purchase Order (PO) from PR
I have defined the process steps (the std Procurement scenario from BPR) but it only talks about performance monitoring, bkg jobs, update errors etc.
I just want to be alerted when the released PR is open for 5 days
Note:
I am sure there are reports in ERP to check this but how do I generate the alert in solman?
Would greatly appreciate the help.
Thanks
This link should help: /people/johannes.fleig/blog/2009/03/21/best-practice-business-process-monitoring-for-procure-to-pay
On selecting the relevant key figure, just double-click on the counter and you can enter the 'X' no days after which you want to be alerted.
Regards
Prasad
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
10 | |
10 | |
8 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.