on 06-30-2009 8:39 AM
hi all,
can you please provide me the T codes for the following reports:
1 Report of engineer wise site attended days
2 Report of free days services and billable services
3 Report of time spent on the project by an individual for specific period
4 Consolidated expenses report
5 History of open project and closed projects with cost incurred
Hi,
1 Report of engineer wise site attended days-S_ALR_87100189 - Actual/Planned Time Series
2 Report of free days services and billable services-ME2j & ME5J
3 Report of time spent on the project by an individual for specific period-S_ALR_87100185 - Actual Costs for Each Month (Current Fiscal Year)
4 Consolidated expenses report- S_ALR_87013532 - Plan/Actual/Variance
5 History of open project and closed projects with cost incurred- S_ALR_87013532 - Plan/Actual/Variance (In the configuration in BS42 t-code define status selection profile for Close and include this in report before executing in the status icon)
Rgds
Sudhir Reddy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.