on 06-30-2009 6:09 AM
Dear All
How to Calculate Cost for the Internal activity.
Please guide me
Regards
Raj
Thanks to all Closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
To calculate cost > goto Activity>Press Ctrl+F10
To see cost--->Press Ctrl+F11
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Raj,
System will automatically caluculate the actual cost after doing the confirmation of the internal activity.
After you have saved the confirmation, the system
· Posts your confirmation for the date entered
· Copies the actual dates to the network or WBS element
· Calculates the actual costs for the posting date.
The actaul cost will be caluculated for the internal from the combination of work center and Activity type.
For Example:
In Activity type KP26 if you define as 5 Rs
While confirmig the internal activity you will mention 10 hrs, then system will caluculate the actual cost as 10x5= 50 Rs.
Regards,
Nag.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
You can calculate the internal activity cost through the work center which you used for that activity. In internal activity you are assigning the work center , activity type and the time.
The activity type and the cost center is linked in the KP26 t.code by giving the value.
The work center has activity type , costcenter and formula to calculate the cost.
So once you enter the time in the intrenal activity it will get calculate based on the formula used in work center.
EX:
Time: 10 Hrs
In the activity type you have given the value per hour 10 Rs
The formula used in work center is ( Time X Value)
So 10X10 = RS 100
Thanks
S.Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
For General cost Activity you no need to calculate the cost. Because in this you just entering the cost , so the same cost will accounted to the activity no calculation needed here.
EX:
Cost Plan
1000 USD
So the same will reflect in the activity cost.
You can check for this in top menu path of the CJ20N select the activity Edit ---> cost --> Plan/ Actual --> Activity element.
Thanks
S.Murali
Hi Raj,
Basically on the lefthand side down you can find Templates for individual objects.
You can drag the cost activity and drop it on the Network.
Inputs for the general costs will be, Cost Element, Amount.
Then goto Edit>Costs> Calculate costs, if it not calculating while saving.
you can create as many Costs Activities as you can......
Rgds
Sudhir Reddy
U can find necessary information in SAP HELP protal...read this http://help.sap.com/erp2005_ehp_03/helpdata/EN/86/98853478616434e10000009b38f83b/frameset.htm
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.