on 06-29-2009 8:03 PM
Hi,
I have a weird issue.
I have 3 materials. one material (fert_mat1) without PPM and other is also FERT (fert_mat2) but has a dependent reqt HALB (halb_mat1).
case 1. fert_mat1 - no ppm
case 2. fert_mat2 -ppm
- halb_mat1
I entered forecast for both materials. when I run a product heuristic for both materials, characteristic requirements are getting transferred to planned order only in case 1 but not in case 2.
for case 1, when I try to convert that planned order to purchase req, the characteristics are getting transferred. In case two, it is completely ignoring characteristics. Is there any badi/fm that I need to apply or is there any oss note for this ? or is there any other reason for this.
thanks
Hi,
As satyajit mentioned, please provide the exact requirement with transaction codes you have operated and what is the exact output you are looking for
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In case 2: did you maintain the procurement type as 'E'?
Actually I did nt get you ..
"for case 1, when I try to convert that planned order to purchase req, the characteristics are getting transferred. In case two, it is completely ignoring characteristics"... can you be more elaborate regarding the actual requirment?
Thanks,
Satyajit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
11 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.