on 06-29-2009 6:13 PM
HI Guys,
Is there any way to exclude the actual cost occured on a project through speicific cost elements on Budget/Actual report? since we are entering the budget without considering the costs occured on those cost elemtns.I know we can exclude cost elements from budget availability control in T.code OPTK. Is there any way to exclude them from the report.
Thanks,
Satya
Edited by: Satya Satya on Jun 29, 2009 7:14 PM
Hi satya,
Check the cost element reports, in the selection screen provide the require cost element to be display in the report.
S_ALR_87013542 - Actual/Commitment/Total/Plan in CO Area Currency.
Hope this may help you.
Regards,
Nag.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
There is only one possibility where you can exclude the cost incurring on certain cost elements in the configuration, by making cost elements exempted from availabiity control.
But there are options in tolerance limits where you can exclude PR or PO etc.
If you realy don't want to have on budget by certain cost elements then you need to exempt those cost elements in the Budget configuration. Cost> Budget>Exempt Cost Elements.
Rgds
Sudhir Reddy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I already specified the cost elements i want to exclude from the availability control. I want to build a report on the actuals less the cost on the excluded cost elements VS Budget.
Does any one know what is the value type for that? I can see in CJ31 assigned values are excluding the cost on the cost elements. But i couldn't find the value type or table for those values.
Can anyone help me on this.
Thanks,
Satya
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.