on 06-29-2009 4:32 PM
I am trying to copy actual cost to planned cost for secondary cost elements via CJ9CS; currently there is a variance.
How can I match my planned cost with the actual cost.
We have already applied OSS note 304119 and we are on ver. 4.7.
Has any one used enhancement COOMKPT4 and function exit EXIT_SAPMKPT4_010 Or is there any other way to copy the actual cost to the planned cost?
Thanks
Amit
Hi,
That is the only transaction for copying actual costs to plan costs.
Try to reconstruct the project using CJEN t-code and check the values.
If not adjusted post it back
Rgds
Sudhir Reddy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sudhir,
Thanks for the quick reply.
CJEN won't work for us, we are trying to find a way to fix CJ9CS.
When we do CJ9CS the price is getting copied over from the price defined in KP26 instead of the Actual price.
We have to find a way for the system to disregard the plan price while copying and just take the actual price.
Any clues how we can do that?
Regards
Amit