I have saved two CO versions of my project. When i go to the project planning board the approved plan column is full of data and looks great but the other version as no information. I have SAPALL so this isn't an authorization issue. Can someone please help me work out was is wrong?
Thanks a lot
Jason
Hi,
Basically there are possibilities of creating Plan version.
1) one you can create in CJ40 by manually feeding the Version ex:0,1,2 etc....
2) create one version in CJ40 and copy the same to another version in CJ9BS.
once the versions are created make the changes of values in the respective versionand save the changes.
Please check the version comparission in S_ALR_87013539 - Project Version Comparison: Plan.
Comming to plan board which fields did you picked up for comparission?
Rgds
Sudhir Reddy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Go to planning board and check which profile has been assigned to "Costs/Revenues" in the "change std values in Project Planning board".
After picking that profile go t-code OPT7 and go to display by selecting the profile and maintain the Cost plan versions in the General data Tab.
later return to planing board check the values......
Rgds
Sudhir Reddy
User | Count |
---|---|
102 | |
14 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.