Hi,

Please update me on how to proceed

I had a VC Dashboard report avaliable in QA & Live portal system.

In Dev system i made few changes to the Dashboard (Adding new buttons,Print,Export)

When i raised a export and imported a request in QA system changes are not imported

Please update

Accepted Solutions (1)

Accepted Solutions (1)

kiran_jakkaraju
Contributor
0 Kudos

Hi

Please use this HOWTO Guide and follow the steps:

[Click View Article|https://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/a0f92042-b36c-2910-d4a3-abfa103564bd]