on 06-28-2009 7:59 AM
Hi
We have performed an unicode conversion In our SAP ECC 6.0 system, after the conversion, the infostructure S906 (copy of S006) was not updated for the period 22nd June to 25th June 09.
Then we regenerated the infostructure S906 using the tcode MCS/ on 26th June and after which the update rules are working correctly in S906.
Now when we run the SOP report for this week, the data is missing for the period 22nd June to 25th June 09.
We have gone thru the note 64636 - to setup the infostructure from the begining, which needs more downtime.
Is there a possibility to get the missing data for the above period only, instead of setting up the infostructure from the beginning.
Thanks & Regards
Senthil
HI Senthil,
Yes their is a possibility to generate missing data only for the specific period as you require.
Firstly find out that your InfoStructure is Updated from which Document Types. For example Sales orders, Deliveries , Billing Docs etc.
Now query all Sales orders from VBAK and Go to OLI7 - (SIS Statistical Setup: Orders) where enter the Info structure which has to be changed and the version Number under which these changes have to be made.
Also Enter Sales Document Numbers between the 2 Dates in the Sales Doc Field.
Enter other Mandatory Fields and Run.
Similarly you need to do for deliveries and Invoices if these are also getting Updated in the Info Structure by using OLI8 and OLI9.
Do let me know if it helps you.
Madhukar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
14 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.