on 06-26-2009 5:48 PM
Hi experts,
I'm trying to manually create a PPM (Production Process Model) into APO (to use it with SNP), however, the value entered in the
Bucket Consumption (Variable) field disappears when I active the PPM. Someone could tell me what I am doing wrong?
First, I created a Resource ( using fields of tab 1 Bucket ) with the following data:
Resource: R
Category (Cat): P - Production
Location: L
Time Zone: BRAZIL
Bucket Dimensn: Mass
Factory Calendar: BR
Bucket Capacity: 96000
Unit: KT - Kilotonne
Number of Periods: 365
Period Type: Day
Days -: 1095
Days +: 1095
ie, a resource with a capacity of 96000 Kilotonne per year.
The PPM I'm trying to create is the following:
Use of a Plan: S - PPM for Supply Network Planning (SNP)
Variable (Single Level Costs): 980,00
Operation: 0010:Produce
Activity: 10:Produce
Product I/O Indicator Consump. Type From Date To Date Unit Var. Consumptn
A O E 01.01.1970 31.12.9999 KT 1000
B I S 01.01.1970 31.12.9999 KT 560
C I S 01.01.1970 31.12.9999 KT 180
D I S 01.01.1970 31.12.9999 KT 260
Mode Primary Resrce Location Unit Fix. dur.
10 R L D 4
Resource Location Unit Var. Bucket Consumpt.
R L KT 1000 (here is the problem)
Prod. Process Model Output Product Date From Date To Planning Locatn Discretization Maximum Lot Size
PPM_1 A 01.01.1970 31.12.9999 L x 9999999
ie, a PPM to produce 1000 KT of A in 4 days that consumes 1000 KT of R resource capacity.
The value of 1000 KT in the field Var. Bucket Consumpt. is not allowed. I could only register values between 0 and 9.
Thanks in advance for help.
Greetings,
Francisco Fonseca.
Edited by: Francisco Fonseca on Jun 26, 2009 1:56 PM
Edited by: Francisco Fonseca on Jun 26, 2009 1:59 PM
HI,
Your variable bucket consumption must be in time units.
since your PPM is created for 1000 KT, you have to maintained the time taken to produce 1000KT in these variable bucket consumption.
Since you have mentioned that it takes 4 days to produce 1000KT, you have to maintain this duration in variable consumption in seconds (4243600).
I think this will solve the problem.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Its a good practice that when you make PPM manually keep fixed duration as '1 Day' (in your mode of activity).
One thing i noticed that you made your resource as bucket resource, which is correct,
but the number you mentioned there (Bucket Capacity: 96000) is not right. What is the unit? It should be in hours (should be 8 or 9 or ).
That means in One day the resource is capable of producing goods for 8/9/ Hours. So, make the change there.
Now in your Mode of activity make fix duration 1 Day.
Components of Activity
Product I/O Indicator Consump. Type From Date To Date Unit Var. Consumptn
A O E 01.01.1970 31.12.9999 KT 1000
B I S 01.01.1970 31.12.9999 KT 560
C I S 01.01.1970 31.12.9999 KT 180
D I S 01.01.1970 31.12.9999 KT 260
Mode of Activity
Mode Primary Resrce Location Unit Fix. dur.
10 R L D 1
Now in resource: put following value
Resource Mode
Resource Location Unit Var. Bucket Consumpt.
R L H 1
You will get an output as 8000 or 9000 (depending on your resource capacity per day, ie 8hr or 9 hr )
and if you put Variable consumption as 8/9 hrs the you will get 1000 KT per day, in that case you put variable material/product consumtion as 250 KT,
so you can get 1000 KT per four day. Variable resource consumption responsible for variable output (variable consumption of FG).
Pls revert if still there is any issue.
Thanks,
Satyajit
Edited by: Satyajit Patra on Jul 2
Edited by: Satyajit Patra on Jul 2, 2009 11:14 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.