on 06-26-2009 3:29 PM
Hi,
Can somebody please let me know what are all pre-requisites ( both for solution manager and satellite systems ) for implementing Change request management.
Best Regards,
Tushar
Hi Thushar,
To use the reporting service for getting data from the satellite systems in your system landscape, the satellite systems must
have the minimum Support Package level:
You will get the information from
http://help.sap.com/saphelp_sm40/helpdata/en/43/70bea480136fcbe10000000a1553f6/content.htm
Also refer
http://help.sap.com/saphelp_sm32/helpdata/en/0c/5b2160f6fa4b83a3674a210b1cdeb0/content.htm .
Regards,
Nibu Antony
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Also take a look at managing change requests with Switchboard (http://www.switchboardsite.com). We love using it.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
You can also try checking this once
/people/dolores.correa/blog/2008/07/26/first-steps-to-work-with-change-request-management-scenario
Regards
Uday
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
No Uday,
I already through with this doc.But it does not mention pre-requisite.
What I need is
1> minimum requirement in Solution manager for ChaRM
2> minimum requirement in satellite system for ChaRM ( above link given by Nibu Antony seems to br for satellite system ).
Best Regards,
Tushar.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.