Dear friends,
can anyone tell me during scheduling from where does material availability date is picked.
thx in adavance
Hi Praveen,
The arrival time at the customer site is calculated as the earliest possible goods receipt time at the customers unloading point on the requested delivery date.
The system calculates backward scheduling as follows:
Requested delivery date minus transit time = Goods issue date
Goods issue date minus loading time = Loading date
Loading date minus transportation lead time = Transportation scheduling date
Loading date minus pick/pack time = Material availability date
Basically the transit time, loading time, and pick/pack time are subtracted from the customeru2019s requested delivery date to calculate the required material availability date.
Backward scheduling is always carried out first. If the material availability date or transportation scheduling date is calculated to be in the past, the system must then use forward scheduling.
Regards,
Chetan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi praveen
First it will do backward scheduling from the requested delivery date ,if d mat. is not available then it will do forward scheduling , then confirms the date at schedule line
Manoj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.