Hi All,

I am using Assembly Processing scenario and having milestone billing. I am able to create a sales order which creating project automatically and milestone are coping in sales order billing plan.

My query is : after creating sales order and automatic creation of project, client changes % amount in billing milestone which is not updating in sales order. Its showing the same amount which has been put in standard milestone.

Let me know how I can update this change in Sales Order billing plan when ever I change billing % in milestone.

Regards,

Atul R. Rajmane

Accepted Solutions (1)

Accepted Solutions (1)

virendra_pal
Active Contributor
0 Kudos

delete the lines in the billing plan plan tab of the sales order

then regenerate the billing plan using milestones

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

After Maintaining billing plan types for milestone billing,Please check the following,

In CJ20N , Create milstone under the activity of WBS,Fill the invoicing percentage in Billing plan section, be sure to tick on sales document date field, then go to the sales order it will copy the data automatically from the milstone .

atul_rajmane
Participant
0 Kudos

HI Vrriendra,

Insted of deleting Billing plan manually can we do this automatically??

I am attaching Milestone to an actvity which assigned to WBS.

Regards,

Atul R. Rajmane

Former Member
0 Kudos

where the milestones are created? is it below the WBS or Network.

rgds

Sudhir reddy