cancel
Showing results for 
Search instead for 
Did you mean: 

Delivery to be picked from JIT

murugan_mgl
Active Contributor
0 Kudos

Hi,

Ineed the delivery to be picked from JIT and not from forecast.How to go about this.

Murugan

Accepted Solutions (0)

Answers (2)

Answers (2)

murugan_mgl
Active Contributor
0 Kudos

closed

Former Member
0 Kudos

Hi,

Please check

[JIT|http://help.sap.com/saphelp_erp2005/helpdata/en/2b/a187c5480b4257ace98444d76d54b0/frameset.htm]

Path for defining schedule line type :

SPRO -> Sales and Distribution -> Sales -> Scheduling Agreements with Delivery Schedules -> Define Schedule Line Types

Thanks,

Raja

murugan_mgl
Active Contributor
0 Kudos

HI,

What happens if i maintain here?

murugan

Former Member
0 Kudos

Murugan,

I just checked and got to know more about JIT,

We can create JIT delivery schedule - where first JIT ( Tcode - JIT1 ) call will be created with JIT quantity . Then JIT delivery ( JITM ) will be created , but not using VL01N . Then pick , pack and PGI .

This is applicable when we are having IS AUTO.

You have to maintin the customer by JITV.

Thanks,

Raja