Order Transfer

Former Member
0 Kudos

Dear Friends,

For any resource which is undergoing plant maintenance order should be blocked for scheduling.

In then current scenario i am testing for a resource wtestwc1_1110_001 which is transferred from ECC.

i created an equipment and assigned testwc1 workcenter.

i created the plant maintenance oder and linked the equipment there. in the location tab it has taken testwc1 workcenter.

in the header tab i have given an other work center testpm1 as the main work center and even in operations tab it displays testpm1 workcenter.

I did CIF Maint order and both the workcenters that is testwc1 and testpm1.

in the resource in SCM for wtestwc1_1110_001 if i go to downtime it is not showing anything there. Pls let me what i have done is correct or shud i do some specific settings in APO.

Pls help me.

Thanks

Vinay

Edited by: vinay on Jun 26, 2009 11:00 AM

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

In the Resource , you can set the lock and then CIF it and try.

Thanks,

nandha