on 06-26-2009 9:35 AM
Dear Friends,
For any resource which is undergoing plant maintenance order should be blocked for scheduling.
In then current scenario i am testing for a resource wtestwc1_1110_001 which is transferred from ECC.
i created an equipment and assigned testwc1 workcenter.
i created the plant maintenance oder and linked the equipment there. in the location tab it has taken testwc1 workcenter.
in the header tab i have given an other work center testpm1 as the main work center and even in operations tab it displays testpm1 workcenter.
I did CIF Maint order and both the workcenters that is testwc1 and testpm1.
in the resource in SCM for wtestwc1_1110_001 if i go to downtime it is not showing anything there. Pls let me what i have done is correct or shud i do some specific settings in APO.
Pls help me.
Thanks
Vinay
Edited by: vinay on Jun 26, 2009 11:00 AM
Hi,
In the Resource , you can set the lock and then CIF it and try.
Thanks,
nandha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
6 | |
4 | |
4 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.