on 04-26-2006 7:33 AM
Get red error when loading Delta data and the red error is:
Record 1 :Time conversion from 0CALDAY to 0FISCPER (fiscal year A1 ) failed with value 20060426
We went to RSA1 -> Source Systems page, right click on the source system, choose Transfer Global Settings, check "Fiscal year variants" and check "Rebuild tables" and then run it twice, but still not helpful that we always get the above red error!
Any idea?
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Kevin,
I am not sure if the fiscal year can have a value A1 as you stated above. If you have the value of A1 for fiscal year then you need to correct the same.
Presuming that it is fiscal year variant A1
Just check in transaction OB29 in BW, whether the variant A1 exists and it has the periods corresponding to the date 20060426.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi Anurag,
You are right that run OB29 on BW, find there is no any period entry for variant A1. Since all the variant should come from R3 by run "Global Transfer Settings" on the source system, I run OB29 on R3 and find the same thing that there is no any period entry for fiscal year variant A1. I will go ahead to ask R3 people to correct it on R3, then conduct the "Global Transfer Settings".
Thanks