When the labor cost of timesheet go to the Actual Cost Line Items report ?

Former Member
0 Kudos

Hi ,

when the user book the time in timesheet on Network / Activity, when this record reflect the actual cost of project ?

After Timesheet Approve via CATS_APPR_LITE

Or after Confirmation

Or after transfer via CATA

Who can tell me the relationship among these three steps ?

Thanks and Regards

Shubin

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

The flow is like this ( if u r using timesheets for confirmation):

CAT2 : Timesheet: Enter Times : User enters the time.

CATS_APPR_LITE : Approval of timesheet

CAT5 : Transfer to Projects.

This will post cost to Projects.

Another way of getting the Actual cost is Confirmation using CN25 or CN29.

Regards,

Former Member
0 Kudos

HI Amit

Is that means only after CAT5 , this cost can be displayed in CJI3 ?

Is that means the confirmation is not mandtory step here ? Why we need do the confirmation ?

Thank you very much !

Shubin

former_member203098
Active Contributor
0 Kudos

Hi Shudin,

Without doing the any approval of time sheet (CATS_APPR_LITE), think which data can be transfer to projects and how actual cost can be appeared against the activity (CJI3)??

Regards,

Nag.

Former Member
0 Kudos

Hi

Confirmation of activity is mandatory step here, without that the actual will not post to the project.

Thanks

S.Murali

Former Member
0 Kudos

Hi,

As I said earlier , these are two different methods to do the confirmation.

1.0 Confirmation via Time Sheets (CATS): Use CAT2 , CAT5

2.0 Confirmation Directly in the Project System :Use CJ20N , CN25

Refer the PDF document in earlier post.

Regards,

Former Member
0 Kudos

HI Murali,

So can I say :

Step 1: CAT2 -- Book time by user

Step 2: CATA_APPR_Lite -- Approve by manager of user

Step 3: CN25 -- Confirmation by who?

Step 4: CAT5 -- Timesheet transfer to Project.

Then after these 4 steps, the labor cost of timesheet go to the CJI3 report ( Actual cost line items report ) ?

Thanks and regards

Shubin

Former Member
0 Kudos

Hi,

If you are using timesheets for Confirmation , then you do not have to do confirmation thru CN25.

Regards,

former_member203108
Active Contributor
0 Kudos

When u r using CATS u dont have to do CN25...CAT5 will confirm the activity...but when u r not using CATS...in that case u will have to manually confirm the activity by CN25.

Former Member
0 Kudos

Hi

Confrimation done by project people, it may be a person responsible for the project. It will vary based on the client requirement.

Always doing manual confirmation using CN25 is good practice.

Thanks

S.Murali