on 06-25-2009 3:48 AM
Dear friends ,
I am quite confused about the confirmation ...
What is the purpose for confirmation ?
The manager already approved the time sheet by CATS_APPR_LITE ? Why there still need to do confirmation ?
Who could tell me the whole process related to the labor in PS ? Like first : Timesheet booking --> Timehseet approve --> .....
Thanks a lot in advance !
BR, Shubin
goto sap help
Edited by: sudhirreddy on Jun 25, 2009 10:33 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Confirmation of activities in PS will post actual cost to project...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.