on 06-23-2009 6:56 PM
hi, Expert:
The user use tcode "CJ20N" to make the confirmation of the activity.
"Confirmation: Degree of processing" don't show the degree that have been confirmed.
Now the user demand when the activity is confirmed,(in CJ20N)
Degree of processing that have been confirmed can be shown!
Regard!.
Hi
You can display the confirmation in CN28 t code based on Network Order / Activity and Confirmation number.
Thanks
S.Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can use CN28 to see the confirmations already done.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.