I have purchased some cost center purchase and assigned to one cost center 1000 and relevant fund center is also 1000.
Now I want to transfer part of the cost to another cost center 2000 with another fund center 2000 through controlling transaction KB11n.
My question is how to transfer the committment from from 1000 to 2000 fund center.
Regards
Suresh A
06-23-2009 2:21 PM
Hi
You can achieve this by defining a derivation rule in FMDERIVE.
Note 666322 should help you to trace the FMDERIVE when KB11N is running. Then you can check the log and see if your target objects (Commitment item, Funds Center, etc) are correctly derived
Kind regards
Mar