add schedule in contract

Former Member
0 Kudos

Hi,

I am not able to add schedule in additional data tab page of a contract(VA42).

When I add it vaishes when I press enter.

Please help.

Also please help me with the table name where I can find the list of all schedule codes that can be added in a contract document.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Check the item category determined in your contract.

Goto VOV7 T.Code.

Select that item category.

Details.

Tick the mark,Schedule lines allowed.

Save.

Now try.

Regards,

Krishna.

Former Member
0 Kudos

Hi,

Just check out if you have maintained any value fo the contract item category in tcode vov4 ( schedule line determination)

regards,

ashish