cancel
Showing results for 
Search instead for 
Did you mean: 

mrp problem

Former Member
0 Kudos

dear all

i have create one project having production wbs id. id-00034-03.

under this wbs id I create sub wbs id (id-00034-03-01,id-00034-03-02,id-00034-03-03)

w r t same material and quantity 1.

i have create wbs bom for all material with id-00034-03. for all the boms valid date is 01-06-2009. project schedule date is from 15-06-2009 to 30-07-2009.

when i run MRP wrt project ie MD51. system calculates only fg material and one assembly. actually bom is create as follows :

fg :

assly 1

assly 2

assly 3

each assembly contains 25 to 40 materials in its own bom.

but system only calculates fg material and first assembly only.

can anybody please explain where i am wrong ?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Please checkout in the MRP view material master of the sub assembly item, what is the MRP type maintained, it should active for MRP.

Regards

Avisek

Former Member
0 Kudos

Hi,

Could you check the status of sub assemblies... it should be released.

Rgds

Sudhir Reddy

Former Member
0 Kudos

all assemblies are released

Former Member
0 Kudos

Hi

Try to change the planning mode to 2 in MD51 and RUN.

Thanks

S.Murali

Former Member
0 Kudos

sir

i try this solution also. but same results as early

Former Member
0 Kudos

Hi

Maintain all raw material and semifinished materials material master settings in MRP 4 view Individual/coll.indicator as 2. and try

Thanks

S.Murali

Former Member
0 Kudos

Hi,

could you let me know onething, do you have only BOM which is assgined to Network activity of first level wbs with qty 1 and runnning MRP or do you have more BOMS assgined to different wbs in the heirarchy.

If so then, check the indicator heirarchy in the MD51 t-code.

if else, give the clear picture waht you are doing..

Rgds

Sudhir Reddy

Answers (1)

Answers (1)

Former Member
0 Kudos

trhanks 2all