Change document for person assignment (Network - tables KBED-KBEZ)

Former Member
0 Kudos

Dear experts,

Is there a way to make the system create automatically change documents when

updating table KBED/KBEZ (person assignment tab in network activity)

Thanks in advance,

Nathalie Winand

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Dears,

I've activated change document in project profile and in network type.

I can see the changes for the total working hours estimation but i cannot see the

individual working hours assigned by PERNR (people).

Is there another place than the network type where i could handle this?

Thanks in advance

Former Member
0 Kudos

Mark change document in 'Parameter for Network type' and 'Project Profile'. And run report CN60.

Sudhir

Former Member
0 Kudos

Hi,

Please activate change Document for Network Type Parameter in OPUV.