on 06-23-2009 8:30 AM
hi all
by mistakely i am crete one wbs bom of today's date. but now i want to change valid date from 01 april 2009. but system wont allow me to do so. please suggest me how to change valid date for wbs bom.
thnks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Delete the line item in the BOM and create the BOM item again with new validity date.
Thanks
S.Murali