Project Delivery

Former Member
0 Kudos

When the FERT mat is attached to activity for Project Delivery...the cost of Mat is reflecting in Planned Cost.

Why this is refelecting in Planned Cost.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi,

When ever any material is attached to activity under component then the price maintained in A/c view is taken as planned cost since there is a possibility that material meight be procured/produced against activity-> network-> WBS element (cost collector) if the budget(i.e. approved planned cost) is provided then this plan cost is considered against that budget.

regards,

Sameer

Answers (2)

Answers (2)

Former Member
0 Kudos

answered

0 Kudos

Hi,

If you dont want to display material planned cost then unchecked the cost rel. in the details screen of material component under tab purch. data.