Rem Order Plan

Dear All,

We know Assigned value in the Report : 13558 is = Commitments + Actuals + Remmaning Order Plan

But where can I find out the rem order plan value ?

If Rem order Plan = Total planned costs - ( Commit + Actuals)

But the figures are not matching

folloiwng are the figures Can anyone plz explan

Planned Costs : 10166262.9

Commitment : 1583389.04

Actuals : 7237161.95

Remenaing order plan: 7528515.27

My budget is over shooting where do I find rem order plan costs line items wise.

regards,

C S

Former Member