MAINTENANCE ITEM

Former Member
0 Kudos

DEAR FRIENDS,

Can any body give the advantages and disadvantages of applying the following methodology for the maintenance plan .:

1- One plan ======one EQUIPMENT ======one maintenance Item.

2- One plan=======one EQUIPMENTS====== Multiple Maintenance Items.

3- One Plan ====== Multiple EQUIPMENTS==== Multiple Maintenance Item.

Accepted Solutions (1)

Accepted Solutions (1)

P745394
Active Contributor
0 Kudos

Hi,

1- One plan ======one EQUIPMENT ======one maintenance Item.

For Ex In plant i have pump which needs to be overhauled every year , what I do Create One maintenance Plan , One Equipment(Pump) in Maintenance item & Start the Plan , Result I get One Maintenance Order at end of one year.

3- One Plan ====== Multiple EQUIPMENTS==== Multiple Maintenance Item.

Suppose same plant has 50 pumps which needs to overhauled every year , This I can Map in SAP preventive maintenance in two ways.

A. Create 50 Maintenance Plans for each different 50 Equipments (Pumps) in Maintenance items & Start All plans , Result I get 50 Maintenance Orders every year ,

or

B.Create One Maintenance Plan , 50 Equipments(Pumps) in 50 Maintenance items & Start the Plan , Result I get 50 Maintenance Orders every year.

if i am using One maintenance plan for multiple equipments its easy to monitor in dead line monitoring , takes less time to get rescheduled , I think it takes less space & less system response time , then why to go for 50 Maintenance Plans with different 50 Equipments in it.

2- One plan=======one EQUIPMENTS====== Multiple Maintenance Items.

This type is preventive maintenance is used Very rear .

Just Take a example I have very precious heavy equipment like Turbine , which I need to Inspect Turbine Rotor from One external Party A & Get this rotor tested by other external Party B every year . As this both Operation execution is Very Costly , when the Maintenance Plan is called I will decide whether to execute this Operation or not.

So how I will Create Maint Plan to Map this , I will Create One Maintenance Plan with Two Maintenance Items ( One Maintenance item will have Turbine as Main header equipment , Task list will have inspection Operations ,External Party A Work Center & Other Maintenance Plan will have same turbine as main equipment , Task list will have Testing Operation with External party B Work Center) , this will Create Two Maintenance Order one for Inspection & One for Testing ,based on budget availability I will release this Maintenance Orders for execution.

Every thing depends on scenario , One thing SAP PM consultant should take care is Use Less Maintenance Plans , More Maintenance items ,less number of tasklists , Easily understanding , easy monitoring , less system loading

Regards,

Former Member
0 Kudos

dear srinivas,

One Plan ====== Multiple EQUIPMENTS==== Multiple Maintenance Item.

but here we need to use object list for assighning individual equipments .then cost cannot be captured for individual equipment .pl clarify

P745394
Active Contributor
0 Kudos

In One Maintenance Item if you are inputting Multiple Equipments in Object List Yes Cost cannot be settled to individual equipments in Object list.

Cost will be settled to equipment in the Reference Object data.

I think its better you use Multiple equipments in Object list only to do & track commmon maintenance activities like Lubrication , Calibration ,GearBox Oil Checking .......... for set of equipments.

You can use user exit to settle cost to equipments in Object list.

Regards,

Former Member
0 Kudos

CAN YOU SUGGEST ANY GOOD BOOK FOR SAP PM .

Former Member
0 Kudos

DEAR,

CAN I CREATE A SUB ORDER BEFORE MY MAIN ORDER IS RELEASED.

Answers (1)

Answers (1)

former_member187991
Active Contributor
0 Kudos

hi

for 1st scenario

better solution for capturing the cost at individua and the scheduling parameter can be chaged which affects only that equipment

2nd scenario

it is not worthy to create one maintenance plan and equipment with multiple maintenane item

3rd scenario

it is used normally for combination of equipments ie all the pump have same type of maintenance with same frequency ,ie all the pump to be serviced once in 3 months

but the scheduling parameter will affect all the maintenance items

regards

thyagarajan

Former Member
0 Kudos

DEAR SIR,

CAN YOU EXPLAIN THE SECOND SCENARIO DISADVANTAGE WITH ANY EXAMBLE

former_member187991
Active Contributor
0 Kudos

hi

if you have created one maintenance plan with multiple maintenance item without technical object then it is like creating maintenance order without technical object which is not useful with respect to the technical object ,it is only used at plan level

regards

thyagarajan

Former Member
0 Kudos

thanks sir,

for the third scenario i didnt understand scheduling parameter will affect all the maintenance items can you please explain this

former_member187991
Active Contributor
0 Kudos

hi

if One maintenance plan consist of multiple maintenance item and equipment ,then the scheduling parameter will be common for all the equipments ,for ex if you change the call horizon it will affect all the maintenance item

regards

thyagarajan