Complete Pipleline steps is not coming

Former Member
0 Kudos

Hi Frnds,

Our basis people installed the PI 7.O few days back, after checking into it, we are not getting the complete pipeline steps for the scenarios,

We are getting only,

-


> 1) Inbound Message ( CENTRAL )

2) Receiver Grouping

3) Response

For almost all the messge in the Moni, whereas it should have more steps.

What could be possible solution so that all the pipline steps comes into the picture.

Please do advice for it.

Thanks

Raj

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

hi \

run tcode sxmb_adm go to IE configuration then specific configuration and then edit mode

new entry

category runtime

parameter LOGGING

value 1

same for sync scenario

category runtime

parameter LOGGING_SYNC

value 1