on 06-21-2009 7:35 AM
Hi Guys,
Iam getting Inconsistent scehduling due to Time zone of Delivering Plant is different than Ship To.
example Plant is in China UTC+8 and Ship To is in US EST (UTC-6).
The MAD date is coming after confirmed delivery date.
Any inputs. help is highly appreciated.
Thanks,
kumar
Hi Kumar,
Please check sap note 1039717
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Kumar,
You say that
I am getting Inconsistant scheduling due to Time zone of Delivering Plant is different than Ship To. example Plant is in China UTC+8 and Ship To is in US EST (UTC-6).
.
Does this mean that the same type of shipment works differently from order to order, or the only problem you have is with the sequencing of MAD and GI date?
The implementation of the solution depends on which APO [Scheduling technique|http://help.sap.com/saphelp_scm70/helpdata/EN/05/f8923945b12c4de10000000a114084/frameset.htm] you are using to schedule the GI date. There is quite a bit of discussion of this matter in [OSS note443500|https://service.sap.com/sap/support/notes/443500] and related notes.
Regards,
DB49
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.