on 06-20-2009 4:23 PM
Hi Friends
what is the difference between CRM_OM_BP_Integrate and BBP_BP_OM_Integrate
what is difference between Start_cleaner,Stop_cleaner and Clean_reqreq_up
Thanks & Regards
Kanni
Hello,
CLEAN_REQREQ_UP:
The report cleans the entries in table BBP_DOCUMENT_TAB where the documents are registered as being in transfer. You can only continue to process SAP SRM documents once the update has been run .
You schedule this report to transfer the status of the creation of follow-on documents for SAP SRM purchasing documents back to the original document. The follow-on documents can have been created either in the back-end system (SAP ERP) or locally in SAP SRM.
At the interval defined by you in Customizing, the system checks whether the documents have been updated and whether you can further process the documents. (The system reads the system table BBP_DOCUMENT_TAB).
BBP_CLEANER:
This program schedules a job to execute the report CLEAN_REQREQ_UP, which is run immediately in the background.
Transaction BBP_BP_OM_INTEGRATE is run after setting up the Organizational Structure
To insure that all of the business partners were created correctly. The system checks the organizational structure regarding missing data like addresses for example. If some inconsistencies are discovered, it shows up. CRM_OM_BP_Integrate was similar transaction but used in earlier versions.
Hope this helps.
Ashutosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.