Hi,

If we use plan-driven procurement, techincal scenario Classic should be used, then it's MM-SUS, current status is, "PR, convert PR into PO" all done in MM (ERP), then transfer to SUS, my question is, could I display and change these POs in EBP?

Regards

jack

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello,

PDP scenario:

1. PR in ECC - Send to SRM for sourcing - RFx in SRM - PO in ECC

2. PO in ECC - Transfer to SUS

3. Change in PO in ECC - Transfer to SUS - Change displayed in SUS

Classic scenario : PO is created in ECC & doesnot exist in SRM, but PO will be transferred to SUS & vendor can view the changes.

Hope this heps.

Thanks

Ashutosh

Answers (1)

Answers (1)

krithika_g
Employee
Employee
0 Kudos

Hi,

In case of Plan-driven procurement, the PO is created in the MM system and transferred to SUS system. SRM system is not used in case of Plan-driven procurement.