on 06-20-2009 6:21 AM
Hi All,
How to do quotation costing?
My client's requirement is to do the costing for the quoation, which they will send to customer.
i.e. to get the cost report.
Regards
Ashis
Ashish,
Activate EK02 Cost condition type for QT document type...... Then u can do costing at QT
Thanks,
Raja
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
There is three types of Cost condition type
EK01
EK02 is manual..... u have to enter this manually and this is statistical
VPRS this is automatic....
So you can see that the objective of all these 3 are different.
EK01 to calculate selling price based on the cost price (EK01 is manually entered)
EK02 just a statistical value of the cost but doesnt have any influence in pricing and is used only for reporting purposes (EK02 also only manually enterable) and
VPRS is automatic cost calculation based on material valuation in the moving avg price or standard price(this is automatically updated based on the Cost of the material.
So if u want automatic then u have to use VPRS......
Thanks,
Raja
Hi,
Thanks again.
I require automatically it should come.So i select VPRS not EK02.
But when for costing inside VOV8, I am giving VPRS in CNDITION TYPE LINE ITEM, it is showing error.
The error is - Only condition types used for 'Pricing' are allowed.
So how I will assign VPRS in that field, so that it will come automatically in quotation?
Regards
Ashis
Hi Asish,
You have to also include EK02 to requirement class then the automatic posting will happen. Put EK02 iin VOV8 and in requirement class.
Please check this
http://help.sap.com/saphelp_dimp50/helpdata/en/90/ba6da4446711d189420000e829fbbd/content.htm
Thanks,
Raja
Edited by: Raja Singh Chhabeda on Jun 21, 2009 11:58 AM