Multiple networks in Sales Order

Former Member
0 Kudos

Hi All,

I am using assm'ly order for projects all configs are in place.

In my project I have multiple networks and WBS as one networks have materials assigments and other has only activities.

I have created a Std WBS with 2 wbs element and 2 std networks.

in CN08 I have assigned the material to network also.

now When I am creating Sales order system is triggering the network but its only taking the network where material is attached and taking the activies of that wbs but not considering the activities of the network which are without material and hence its not picking that wbs as well.

kindly let me know where I am going wrong.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

in Assembly processing only header operated networks are used.

when through CN08 the network is attached to Material. At the time of saving of sales order only that network and the related contributors below it are copied as new component in project following the delivery dates appeared in sales order line item, means the networks which are parallel or above that are not considered.

Hence check the structure of standard network.

Regards,

Sameer