In the budget reports (T code:S_ALR_87013558), Assigned overall = Actual overall + Commitment overall .

Taxes and duties are included in assigned over all value or not ?

Thanks,

Hari

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

I got the answer myself

Former Member
0 Kudos

Hello All,

I got the answer for this, in Both Actual overall, Commitment overall , taxes and duties are included.

as a result in Assigned overall also contains taxes and duties.

Thanks for all for the responses.

Hari

pradeep_mahamuni
Contributor
0 Kudos

in actual overall only those cost are included which are not getting back from government

eg. CENVAT, excise.

only cost loaded on material and services will be the part of actual cost.

Former Member
0 Kudos

Hi Pradeep,

Perfect answer from pradeep.

Rgds

Sudhir reddy

Former Member
0 Kudos

Hi Hari,

taxes and duties are not included in Overall actual. those entries hit different GL.