Hi,
we are using MS project ,we have projects which consists of more baselines like baseline 1, baseline 2, and baseline 3.
dates in each baseline are different.
how to manage more than one baseline dates in sap ps?
thanks!
Harsh
Hi Harsh,
In SAP PS, We can use Base line dates either in Basic dates or in Forecast dates. in CJ20N, open project and goto settings --> set of dates --> select either basic dates or forecast dates.
you can maintain base line in any one of them and then freeze and maintain as base line dates. If you want to maintain more base lines for a project use project versions and simulation versions functions to create more number of schedules. based on the requirement you can simulate the schedule dates into operative project from its simulation version,
Hope this clears you !
Br,
Hari.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.