Hi Gurus,
I need a clarification... as per the client's business requirements, cost planning is to be executed in various versions before it is finally approved. As of now it is decided to copy this into zero version (approved version). What will happen if components & services are assigned to network when real execution starts ?
Let me give an example, Unit cost planning is executed for $1000. This cost plan is copied into zero version. when the user start executing the project, they assigned components & service in the network amounting to $800. As system takes this planning directly to zero version, will the total planned cost will become $1800 ? If so, should i not take the approved cost plan into zero version instead to copy into some other version and only use Plan 1/Plan 2/ Actual Report to see the comparison ?
Whether my understanding is correct ?
Regards,
Vinodh
Hi Vinod,
Goto OPSV ( Define Order Value Updating for Orders for Projects ), remove the Check box "addit" for Order category - 20.
You can copy the Planned cost from other versions to active version - "0" but you can keep order settings to avoid appending planned cost to WBS Element Level. So, even though user do network costing, network planned cost not appended to WBS Element. Hence your initial approved planned cost remains same and you can see in all reports.
Hope this clears you !!
Br,
Hari.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Hari.
Closed.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
14 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.