Hi Guys,

I am getting this error in an activity: message class C7 and number 066 " Error during scheduling splits"

The activity is for CATS time booking, The activity has must start on and must finish on contraints, and the actual start date is 3 days after the must start date. The activity has persons assigned to it. The error occurs when the user tries to delete or add an assignment or if any of the scheduling parameter is changed triggering automatic schdueling while saving.

Any idea how to fix this or reason for this error.

Regards,

Paval.

Accepted Solutions (0)

Answers (2)

Answers (2)

ansar_shaikh2
Contributor
0 Kudos

Please let us know the solution for the same.

Did you problem gets resolved? tell us how?

regards,

ahs

Former Member
0 Kudos

Hi Paval,

This error is occurring because you might have assigned Workcenter which has HRMS linked to it and this Workcenters have persons assigned to it. Goto the corresponding Network activity and look for one Person assignment tab (got inserted because of this Workcenter assignment with HR). Assign the no. of hours for each person. your problem will be solved or remove the No. of persons assigned in the Internal tab for this Workcenter (if u don't want to do this splitting).

Get back if you have any issues.

Regards,

L.Balachandar

Former Member
0 Kudos

Hi LB,

The people assignments in the acitivity are all available in the Workcentre with work and duration in the activity and in the specified period. Can you please let me know how does the deletion of people assignment in the work centre helps solve this issue.

Regards,

Paval.

Former Member
0 Kudos

Hi Kanagavel,

A split for a person is scheduled using the available working time of a person, which is calculated from information pertaining to the person maintained in HR - Personnel Time Management.

Because HR - Personnel Time Management information is used, it is necessary to configure certain parts of the R/3 Component HR Personnel Time Management. It is not necessary to use HR Payroll!

A split is not scheduled using the operation work center information.

The infotype 'Planned Working Time' with a Work Schedule Rule must be maintained for the person. This infotype has the number 0007.

This is necessary for the generation a Personal Work Schedule for the person.

Go to PA20 Transaction and check whether the person is maintained by Infotype planned working Time-007, If maintained check whether the infotype must contain a Work schedule rule, if not maintain the same.

You can generate a work schedule rule using PT01 as well.

Even You can use the function module HR_PERSONAL_TIME_LIST to test whether HR provides the necessary information for the scheduling of splits to the capacity planning component in logistics.

go through this and revert back if the issue still persists.

Rgds

Sudhir Reddy Addaganti

Former Member
0 Kudos

Hi Paval,

What I meant is not to remove the persons from the Workcenter.

1.If you are assigning persons in the "Person assignment" tab then give no. of hrs. per person. or

2. If you do not want the personnel details and only the Internal manpower cost is to be calculated then do not assign any persons in the "Person assignment" tab or

3. If you do not want to calculate the manpower cost, remove the quantity from the No. field in the internal tab of activity in which this workcenter is assigned.

Regards,

Bala.

Former Member
0 Kudos

Hi Paval,

Refer SAP Note: 543362

Rgds

Sudhir reddy.

Former Member
0 Kudos

Hi Paval,

Does the note helped you to resolve the your issue?