on 06-18-2009 7:03 PM
Hi,
By default, the deployment run considers regular calendar which does not consider holidays or weekends.
Is there a way to make it consider the source location factory calendar, so that holidays and weekends are considered while deploying?
Hi APJ999,
Check & confirm whether sap note 710374 is applicable to you.
Regards,
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Assign the transportation calender in transportatio lane as well under means of transport.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Thanks for the response.
I have already attached the shipping, production and warehouse calendar and also the transportation calendar in the means of transport in the transportaion lane.
But it still does not consider factory calendar. It does not take weekend and the holidays into account for deployment purpose.
Hi APJ999,
In location master of APO, under calendar tab, maintain shipping calendar & create time stream accordingly & retry deployment
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.