Revenue Planning

Former Member
0 Kudos

Dear all:

i created a project with profile IECPP01, and created a Network with profile IECPP01 and assigned it to a Billing WBS element,

then i assigned 3 milestones with Usage PS01 for partial billing to 3 activities in the network

then i created a sales order with Order Type ZEC3 in Sales Area 4000, 40, 00 , then maintained a Billing Plan for the item by copying the milestone dates as billing dates.

HOWEVER, no planned values for Revenues in the project

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

thank u all guys

i solved it

it was about Item Category in the Slaes Order

Former Member
0 Kudos

Yes, as suggested by Hari check the Automatic Revenue planning from Sales Order in OPSB. Make sure that WBS is a billing element.

Hope this helps.

Thanks

Sarang

Former Member
0 Kudos

the chek box "from sales order" in the tap page "Automatic Revenue Planning" in the planning profile is ACTIVE

Former Member
0 Kudos

Hi Byalya,

Tick from Sale Order check box in the planning profile using in your project and again try to create a new project and check the planned revenue.

Hope this helps you,

Br,

Hari

Former Member
0 Kudos

the chek box "from sales order" in the tap page "Automatic Revenue Planning" in the planning profile is ACTIVE

former_member203108
Active Contributor
0 Kudos

Have u maintained revenue element for billing in planning profile?... If not maintain it

Former Member
0 Kudos

yaaaaaa

thank you

i solved it

it was a problem in the Item Category in the Sales Order