Releasing standard network automatically when integrated in released proj.

Former Member
0 Kudos

Hi Guys,

I am facing the following problem:

In the PS module we have created several Def/WBS standard structures with NW and activities.

Once we have copied the standard template in a new operative structure, we add some new standard networks and rebuild the structure in order to fulfil the new operative project needs. Once done we release the project definition in order to release all objects in the projects, i.e. WBS, Networks, activities and material.

For some reasons and after the releasing phase we have to had new standard networks somewhere in the project structure on WBS level.

The problem we face then is that the new network and all the related activities do not get the release status as all other objects but still remain in the open status. How is it possible to set automatically the release status in the new network, as far as the project definition is released?

Thank in advance for your precious inputs/solutions.

Best regards

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Thank you both for giving this helpfull tip.

See you and best regards

Pierre-Alain

Former Member
0 Kudos

Hi Pierre,

Check the option in OPSC to release the networks immediately after the creation. This will release the networks as soon as they are created.

Hope this helps you.

Regards

K Ramaiah

Former Member
0 Kudos

Hi,

In network Type , tick " Release Immediately" indicator ( T Code OPSC ).

The network will be automatically assigned "Released" status when they are created.

Regards,