Hi all,

I want to know about the Commitment managment in PS so that i can implement it in our organization's projects.

Pl explain me the process with t codes as wel.

Best Regards,

Vishal

Accepted Solutions (1)

Accepted Solutions (1)

stheurkar
Active Contributor
0 Kudos

Hi,

In T-code OKKP check whether you have ticked Projects & With Commitment Management (W. Commit. Mgt.) indiacators for your controlling area. Also make Commitment Management components active.

By doing above setting commitment management will activate for projects.

Normally this customizing will be done by fico consultant.

Regards,

Sandeep

Former Member
0 Kudos

Thanks, i know the confiuration for it, can you pl explain me the process how it works in PS.

Rgds,

vishal

Former Member
0 Kudos

Hi, thanks for the reply,

Our organization have a 25 project and i want to activate this commitment managment to perticuler one project is it possible for one project.

Pl revert.

thanks,

vishal

Former Member
0 Kudos

Commitment management is activated at controlling area level and hence it cannot be activated or deactivated at project level.

Sarang

Answers (1)

Answers (1)

Former Member
0 Kudos
Former Member
0 Kudos

Thank you very much, i have understood much about material procurement commitment, but can u explain me how it will work with PS.

Pl revert.